The BOARD OF PARK COUNTY COMMISSIONERS located in Fairplay, Colorado invites statements of qualifications for general construction services from selected firms to submit competitive bids to perform the duties of the general contractor to construct the new PARK COUNTY COMMUNICATIONS CENTER. Project The construction of the new PARK COUNTY COMMUNICATIONS CENTER that meets all local codes and requirements the Board of Park County Commissioners of Park County Colorado.
Bley Associates, Architects/Planners, Inc have prepared construction documents for the new Park County Communications Center to be located on a one acre hill site accessed from Castello Ave in the Town of Fairplay Colorado. The project consists of a single level, noncombustible type 2B, B occupancy, 2006 International Building Code, 8550 SF building. The building is to provide exterior and internal security for staff to work in the combination 911 dispatch, IT Data Center, and EOC Emergency Center facility with limited public access. The scope of work shall include, but is not limited to the following: on site parking; landscaping and site drainage, a secured tower utility court for operational equipment; dirtwork, utility services, drainage structures, paving and site features, xeriscape irrigated plantings and rock landscaping; lightweight load bearing cmu/cavity insulated/brick veneer exterior wall construction, steel post and beam framing system, and insulated standing seam metal roof; light gauge metal stud framing, drywall portioning, painting, acoustical and gypsum board ceilings, prebuilt cabinets, casework, millwork, and floor and special wall finishes; zoned HVAC units, computer room air conditioning; building plumbing for locker/public restrooms and break rooms; automatic wet fire sprinkler system including provisions for a dry clean suppressions system for the data center and a preaction delay system for the dispatch center; electrical provisions for power, lighting, low voltage life safety (FSD), communications security systems, emergency power generator, backup UPS, systems wiring for 911 Dispatch area, IT Data, and Emergency Operations Center.
Schedule The schedule for the selection process is as follows:
Communications/IT Building Timeline
3/21/2011 |
2:00 pm-6:00 pm |
Building Drawings to be issued to Pre-Qualified Contractors |
3/28/2011 |
1:00 pm - 3:00 pm |
Pre-bid Conference, Fairgrounds, 880 Bogue, Fairplay, CO, Contrators, Subcontractors and Suppliers are invited |
4/27/2011 |
10:30 am |
Bids to BOCC. Bids opened during BOCC Work Session |
4/27/2011 |
11:15 am |
Furnture, Fixtures & Eqipment (FFE) Bid Opening |
5/11/2011 |
10:30 am |
BOCC to interview contractors |
5/12/2011 |
9:00 am |
BOCC to award Bid |
5/23/2011 |
|
Construction to Begin |
12/31/2011 |
|
Building Complete | Please email with any questions you may have.